How the cost is worked out
Cost = length × width × (thickness ÷ 12) ÷ 27 × price per yard + fees
A worked example
A slab 20 by 10 feet and 4 inches thick is 2.47 cubic yards. With 10% extra that is 2.72 yards. At $160 a yard the concrete costs about $435, which is $2.17 per square foot.
Good to know
- This is the concrete only. Forms, base gravel, reinforcing, the pump and the finishing labor usually add up to more than the concrete itself.
- Plants often charge a short-load fee for orders under a certain size, and extra if the truck waits past a set time. Have the forms ready.
- Higher strength mixes, fibre and additives for hot or cold weather all raise the price per yard.
- Round your order up to the next quarter yard. Running short costs far more than a little left over.
Common questions
Is it cheaper to mix bags?
Only for small jobs. Past about a cubic yard, ready-mix is usually cheaper and always easier. The concrete slab calculator shows the bag count.
How we know this calculator is right
Before this calculator went on the site, 7 answers were worked out separately from its code, by hand or straight from the formula above. Each time this page loads, your own browser runs the calculator on those same numbers and compares. Turn on JavaScript to see the comparison.
See every check
| Numbers used | Result | Worked out separately | This calculator |
|---|
What this proves: the calculator does the arithmetic of the formula shown, correctly. What it cannot prove: your measurements, or figures such as coverage per bag, waste and spacing, which are typical starting values you can change. Go by the product label and your local code.